CMA Final · Strategic Cost Management · Just in Time (JIT)
Under JIT, a cell at Narmada Engineering has a set-up time of 2 hours per batch and runs 10 batches a month. Machine cost is Rs 600 per hour. Through set-up reduction, the set-up time falls to 30 minutes per batch. What is the monthly saving in set-up cost?
The monthly saving is Rs 9,000. Set-up time falls by 1.5 hours per batch, giving 15 hours saved across 10 batches, and at Rs 600 per hour that is Rs 9,000. Rs 12,000 is merely the original set-up cost, not the saving.
- ARs 9,000Correct
- BRs 12,000
- CRs 18,000
- DRs 15,000
Explanation
Time saved per batch = 2 hours - 0.5 hour = 1.5 hours. Over 10 batches = 15 hours. At Rs 600 per hour, saving = Rs 9,000. Check: old cost 12,000 less new cost 3,000 = 9,000. Rs 12,000 is the old cost, not the saving.
Did you get it right without looking?
One question tells you little. A timed set on Just in Time (JIT) shows your real accuracy, how long you take and where you lose marks.
More Just in Time (JIT) questions
- A pump manufacturer in Coimbatore moves to a JIT system. Which of the following is the most characteristic feature of the new production app…
- Sundaram Auto Parts has annual demand of 12,000 units and currently has a set-up cost of Rs 1,800 per set-up and carrying cost of Rs 12 per …
- Which of the following is a defining feature of a Just in Time (JIT) purchasing arrangement with suppliers?
- Which one of the following is a defining feature of a JIT purchasing arrangement between a manufacturer and its suppliers?
- A manufacturer moving to Just in Time wants to compare its purchasing approach before and after. Which of the following is a characteristic …
- Which of the following is the primary reason a firm adopting Just in Time (JIT) purchasing typically negotiates long-term contracts with a s…