Which statement about a flexed budget is correct?

A flexed budget adjusts the budgeted revenue and variable costs to the actual level of activity, keeping fixed costs unchanged, so actual results are compared with a budget for the same output. This gives more meaningful variances than comparing with the original fixed budget.

  1. AIt adjusts budgeted variable costs to the actual activity level so actual results can be compared on a like-for-like basisCorrect
  2. BIt is prepared at the start of the year to give managers a fixed target regardless of activity
  3. CIt adjusts budgeted fixed costs in proportion to actual activity
  4. DIt replaces actual results with standard costs in the financial statements

Explanation

A flexed budget recalculates revenue and variable costs for actual activity, leaving fixed costs unchanged within the relevant range. This allows meaningful variance analysis. A fixed budget at the start of the year is the original budget, and flexing fixed costs is incorrect.