ACCA Applied Knowledge · Management Accounting · Standard costing system
Hartley Co budgeted to produce 5,000 units with variable costs of $8 per unit and fixed costs of $20,000. Actual production was 5,600 units. What is the flexed budget total cost for 5,600 units?
The flexed budget total cost is $64,800. Variable cost is flexed to actual output, 5,600 units at $8 giving $44,800, while fixed costs stay at the budgeted $20,000 because they do not vary with activity in the relevant range. The two are then added together.
- A$64,800Correct
- B$44,800
- C$60,000
- D$40,000
Explanation
Flexed variable cost = 5,600 x $8 = $44,800. Add fixed costs of $20,000 (unchanged) to give $64,800. $44,800 omits fixed costs. $60,000 is the original budget (5,000 x 8 + 20,000 = 60,000) not flexed.
Did you get it right without looking?
One question tells you little. A timed set on Standard costing system shows your real accuracy, how long you take and where you lose marks.
More Standard costing system questions
- A company's standard labour rate was $14 per hour. Because of a shortage of skilled workers, it used more highly skilled staff paid $16 per …
- Which of the following is a recognised advantage of using a current standard rather than a basic standard when setting standards?
- Budgeted sales were 1,000 units at a standard selling price of $50 and standard cost of $35 per unit (absorption costing). Actual sales were…
- Mortlake Co makes a single product. The standard for each unit is: direct labour 3 hours at $14.00 per hour; variable overhead 3 hours at $2…
- A company makes one product. Each unit needs 4 kg of material that costs $5 per kg. Normal wastage is 20% of the input material. What is the…
- A company sets its standard labour rate using a standard that assumes all staff are paid at grade B, $12 per hour. Production in the period …