ACCA Applied Knowledge · Management Accounting · Standard costing system

Hartley Co budgeted to produce 5,000 units with variable costs of $8 per unit and fixed costs of $20,000. Actual production was 5,600 units. What is the flexed budget total cost for 5,600 units?

The flexed budget total cost is $64,800. Variable cost is flexed to actual output, 5,600 units at $8 giving $44,800, while fixed costs stay at the budgeted $20,000 because they do not vary with activity in the relevant range. The two are then added together.

  1. A$64,800Correct
  2. B$44,800
  3. C$60,000
  4. D$40,000

Explanation

Flexed variable cost = 5,600 x $8 = $44,800. Add fixed costs of $20,000 (unchanged) to give $64,800. $44,800 omits fixed costs. $60,000 is the original budget (5,000 x 8 + 20,000 = 60,000) not flexed.