Which type of standard is most likely to motivate employees while remaining realistic for a standard cost card?

An attainable standard is most likely to motivate staff. It allows for normal wastage, idle time and breakdowns, so it is demanding but achievable. Ideal standards are usually unreachable and demotivating, while basic standards that never change become out of date and unhelpful for control.

  1. AIdeal standard, assuming no waste or idle time
  2. BAttainable standard, allowing for normal losses and reasonable inefficiencyCorrect
  3. CBasic standard, left unchanged for many years
  4. DLast year's actual cost, used without adjustment

Explanation

An attainable standard is challenging but achievable, allowing for normal waste and idle time, so staff are likely to be motivated. Ideal standards usually cause adverse variances and demotivate; basic standards become outdated and give little useful information.