Which statement about free float and total float in a CPM network is correct?
Free float is the delay an activity can absorb without delaying the earliest start of the following activities. It can never exceed total float, which is the delay allowed without delaying the whole project.
- AFree float can exceed total float
- BFree float is the delay possible without delaying the earliest start of any succeeding activity, and it never exceeds total floatCorrect
- CFree float is always equal to total float on the critical path only if costs are minimum
- DFree float is the delay possible without delaying project completion
Explanation
Free float is the time an activity can be delayed without affecting the earliest start of its successors; it is at most the total float. The definition in the last option describes total float instead.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- Which of the following best describes resource levelling in project scheduling?
- The critical path of a project at Kaveri Constructions consists of three activities with expected times of 10, 14 and 16 days, and variances…
- An activity has optimistic time 6 days, most likely time 9 days and pessimistic time 18 days. What is the variance of its duration under PER…
- A project has a total budget at completion (BAC) of ₹20,00,000. Earned value to date is ₹8,00,000 and actual cost is ₹10,00,000. Assuming th…
- In the project life cycle, which phase is mainly concerned with defining objectives, scope, deliverables and obtaining approval to proceed?
- A construction firm in Pune has completed building a warehouse and is now handing it over to the client, obtaining acceptance, releasing sta…