ACCA Applied Knowledge · Management Accounting · Flexible budgets

A company budgets for 4,000 units: variable production cost $10 per unit, a step-fixed supervision cost of $9,000 per 5,000 units of output or part thereof, and other fixed costs of $20,000. Activity is flexed to 6,200 units. What is the total flexed budget cost?

The total flexed cost is $100,000. Variable costs are $62,000, supervision needs two steps of $9,000 because output exceeds 5,000 units, giving $18,000, and other fixed costs are $20,000.

  1. A$99,000Correct
  2. B$91,000
  3. C$90,000
  4. D$100,000

Explanation

Variable cost = 6,200 x 10 = $62,000. Supervision: 6,200 units needs two steps = $18,000. Other fixed = $20,000. Total = $100,000. Check: 62,000+18,000+20,000 = $100,000, so the key is $100,000 and not the options with one step.

Did you get it right without looking?

One question tells you little. A timed set on Flexible budgets shows your real accuracy, how long you take and where you lose marks.

More Flexible budgets questions