ACCA Applied Skills · Performance Management · Planning and operational variances
A company set a standard material price of $10 per kg. Due to a market-wide shortage, the actual price paid was $12 per kg, and the ex-post (revised) standard price was agreed as $11.80 per kg. Which of the following statements about the price variances is correct?
The planning variance is $1.80 per kg adverse (original $10 versus revised $11.80) and the operational variance is $0.20 per kg adverse (revised $11.80 versus actual $12). Together they equal the total $2.00 adverse price variance.
- AThe planning variance is $1.80 per kg adverse and the operational variance is $0.20 per kg adverseCorrect
- BThe planning variance is $2.00 per kg adverse and the operational variance is $0.20 per kg favourable
- CThe planning variance is $0.20 per kg adverse and the operational variance is $1.80 per kg adverse
- DThe planning variance is $1.80 per kg favourable and the operational variance is $0.20 per kg adverse
Explanation
Planning variance = original standard $10 minus revised standard $11.80 = $1.80 adverse per kg. Operational variance = revised standard $11.80 minus actual $12.00 = $0.20 adverse per kg. The two sum to the total $2.00 adverse. Option C reverses the two figures.
Did you get it right without looking?
One question tells you little. A timed set on Planning and operational variances shows your real accuracy, how long you take and where you lose marks.
More Planning and operational variances questions
- Which variance is classed as an operational variance when a revised (ex-post) material price is used as the benchmark?
- Brindle Co budgeted 3 labour hours per unit at an original standard rate of $10 per hour. The ex-post (revised) standard is 3.5 hours per un…
- Tarn Co originally budgeted a material price of $5 per litre. The revised ex-post price was $6 per litre. The purchasing manager bought 10,0…
- Tarn Co's original standard price for material was $8 per kg. The ex-post price was $9 per kg. Actual purchases were 5,000 kg at $8.70 per k…
- Marsh Co uses a revised standard labour rate of $14 per hour. For the period, 5,200 hours were paid at $14.50 per hour, of which 300 hours w…
- Which of the following labour variances would most appropriately be classified as a planning variance rather than an operational variance?