A factory makes standard soap bars continuously, with fixed routing and same sequence of operations for all units, and the schedule is drawn once for a long period. This type of scheduling is most appropriately called:
This is flow-shop or continuous mass production scheduling. Because the product is standard and every unit follows the same fixed sequence of operations, one schedule can serve for a long period. Job-shop scheduling is for varied custom orders needing frequent re-sequencing.
- AJob-shop scheduling with frequent re-sequencing
- BProject scheduling using crashing
- CFlow-shop (continuous or mass production) schedulingCorrect
- DBackward scheduling of one-off orders
Explanation
Standardised product, fixed routing and continuous output are features of flow or mass production scheduling, where schedules are stable. Job-shop scheduling suits varied, custom orders and needs frequent re-sequencing, so option A is wrong.
Did you get it right without looking?
One question tells you little. A timed set on Scheduling and Queuing Models shows your real accuracy, how long you take and where you lose marks.
More Scheduling and Queuing Models questions
- Four jobs with processing times A = 5, B = 2, C = 4, D = 3 days are loaded on one machine from time zero. Their due dates are A = 14, B = 4,…
- In production scheduling, a Gantt load chart is primarily used to show which of the following?
- In a queuing system at a bank branch, customers arrive randomly and are served by a single teller in the order of arrival. Which queue disci…
- In production scheduling, which of the following best describes the main purpose of scheduling?
- A single-server M/M/1 clinic has arrival rate 6 patients per hour and service rate 8 patients per hour. What is the average time a patient s…
- Four jobs are processed on M1 then M2 (hours): A (5, 2), B (1, 6), C (9, 7), D (3, 8). What is the optimal sequence under Johnson's rule?