Four jobs are processed on M1 then M2 (hours): A (5, 2), B (1, 6), C (9, 7), D (3, 8). What is the optimal sequence under Johnson's rule?

The optimal sequence is B-D-C-A. B has the smallest time (1 on M1) and goes first, A has the next smallest (2 on M2) and goes last, D (3 on M1) takes the next front slot, leaving C in the remaining position.

  1. AB-D-C-ACorrect
  2. BB-D-A-C
  3. CD-B-C-A
  4. DA-C-D-B

Explanation

Smallest time is 1 (B on M1), so B goes first. Next smallest is 2 (A on M2), so A goes last. Next is 3 (D on M1), so D goes second. C remains in third place. Sequence B-D-C-A. Putting A before C ignores that A's minimum is on M2.