In production scheduling, a Gantt load chart is primarily used to show which of the following?

A Gantt load chart shows the work allotted to each machine or work centre over time, revealing loaded and idle periods. It is a scheduling and loading tool, not a tool for costing, probability analysis or order quantity decisions.

  1. AThe cost of each job against its selling price
  2. BThe work assigned to each machine or work centre against time, showing its load and idle periodsCorrect
  3. CThe probability distribution of job completion times
  4. DThe optimum order quantity for each product

Explanation

A Gantt load chart plots machines or work centres against a time scale and shows the work allotted to each, so planners can see loading and idle time. It is not a costing or inventory-ordering tool, so options on cost, probability or order quantity do not describe it.