CMA Intermediate · Operations Management and Strategic Management · Designing of Operational Systems and Control
A firm compares three sites using a weighted factor rating. Weights: labour 0.5, transport 0.3, power 0.2. Scores out of 100 for Site X are 70, 80, 60; Site Y 90, 60, 50; Site Z 80, 70, 90. Which site should be selected and what is its score?
Site Z should be selected with a weighted score of 79. Multiplying each factor score by its weight gives X 71, Y 73 and Z 79, so Z ranks highest. Site Y at 73 is the next best but still lower.
- ASite X with 71
- BSite Y with 73
- CSite Z with 79Correct
- DSite Z with 80
Explanation
X = 35+24+12 = 71. Y = 45+18+10 = 73. Z = 40+21+18 = 79. Z has the highest weighted score. The 80 option comes from the unweighted score of Z's first factor, a wrong base.
Did you get it right without looking?
One question tells you little. A timed set on Designing of Operational Systems and Control shows your real accuracy, how long you take and where you lose marks.
More Designing of Operational Systems and Control questions
- In the product development process, which activity is carried out immediately after a firm has generated a set of product ideas and before i…
- Which decision is classified as a strategic-level (long-term) decision in operations management rather than a tactical or operational one?
- A firm uses a shared kitchen to serve both dine-in customers and a cloud-kitchen delivery app. Which feature most clearly distinguishes serv…
- A manufacturer in Chennai decides to build extra capacity ahead of expected demand growth, accepting the risk of idle capacity. Which capaci…
- In operations management, the transformation process converts inputs into outputs. Which of the following correctly pairs an input with the …
- Concurrent (simultaneous) engineering in new product development is mainly intended to: