CMA Intermediate · Operations Management and Strategic Management · Designing of Operational Systems and Control
A textile mill in Surat services its looms only after they break down and stop production. Which type of maintenance does this describe?
This is breakdown maintenance, because the mill repairs looms only after they fail and stop. Preventive maintenance would involve servicing at planned intervals before failure, and predictive maintenance would use condition monitoring data, neither of which is being practised here.
- APreventive maintenance
- BBreakdown maintenanceCorrect
- CPredictive maintenance
- DRoutine inspection maintenance
Explanation
Maintenance carried out only after equipment fails is breakdown (corrective) maintenance. Preventive maintenance is scheduled in advance at fixed intervals, and predictive maintenance relies on condition monitoring. Neither of these applies since the mill waits for failure.
Did you get it right without looking?
One question tells you little. A timed set on Designing of Operational Systems and Control shows your real accuracy, how long you take and where you lose marks.
More Designing of Operational Systems and Control questions
- A manufacturer in Chennai decides to build extra capacity ahead of expected demand growth, accepting the risk of idle capacity. Which capaci…
- In operations management, the transformation process converts inputs into outputs. Which of the following correctly pairs an input with the …
- Concurrent (simultaneous) engineering in new product development is mainly intended to:
- A plant in Coimbatore has a design capacity of 2,000 units per week and an effective capacity of 1,600 units per week. Its actual output las…
- Sharma Auto Parts has a design capacity of 1,000 units per day. Effective capacity is 800 units per day and actual output is 680 units per d…