Skip to content

CMA Intermediate · Operations Management and Strategic Management · Production Planning and Control

A Kanban system for a component has daily demand of 400 units, lead time (production plus waiting and transit) of 0.5 day, safety factor of 10% and container capacity of 20 units. The number of Kanbans required is:

The number of Kanbans required is 11. Using demand of 400 units per day, lead time of 0.5 day and a 10% safety factor, requirement is 400 x 0.5 x 1.10 = 220 units, which divided by the container size of 20 gives 11 Kanbans.

  1. A10
  2. B11Correct
  3. C12
  4. D20

Explanation

Number of Kanbans = Demand x Lead time x (1 + safety factor) / Container size = 400 x 0.5 x 1.10 / 20 = 220/20 = 11. Ignoring the safety factor gives 10, which is wrong because stock cover is required.