CMA Intermediate · Operations Management and Strategic Management · Production Planning and Control
A plant has 2 shifts of 8 hours each per day and works 25 days a month. It has 10 machines. Effective capacity is 80% of design capacity because of planned maintenance and set-ups. Design capacity is based on all machine hours available. Actual output in a month is 3,200 machine-hours. What is the capacity utilisation (actual output as % of effective capacity)?
Capacity utilisation is 100%. Design capacity is 10 machines x 16 hours x 25 days = 4,000 machine-hours; effective capacity is 80% of this, or 3,200 hours. Actual output of 3,200 hours equals effective capacity, so utilisation against effective capacity is full.
- A80%
- B100%Correct
- C64%
- D125%
Explanation
Design capacity = 10 x 16 x 25 = 4,000 machine-hours. Effective capacity = 80% x 4,000 = 3,200 hours. Utilisation = 3,200/3,200 = 100%. Using design capacity as the base would give 80%, which is efficiency-type confusion, not utilisation against effective capacity.
Did you get it right without looking?
One question tells you little. A timed set on Production Planning and Control shows your real accuracy, how long you take and where you lose marks.
More Production Planning and Control questions
- In an MRP system, a component takes 2 weeks to procure and its net requirement of 400 units arises in week 8. When should the planned order …
- In production control, what is the main purpose of the 'follow-up' or 'expediting' function?
- Which statement about Gantt charts in production control is correct?
- Ananya Appliances plans to assemble 200 units of a product in week 6. Each unit needs 3 units of component C. Stock on hand is 150 units and…
- Which statement about capacity planning is correct?
- A Kanban system for a component has daily demand of 400 units, lead time (production plus waiting and transit) of 0.5 day, safety factor of …