A machine under breakdown maintenance has an expected 4 breakdowns per month, each costing Rs 5,000. A preventive maintenance programme costing Rs 9,000 per month would cut breakdowns to 1.5 per month. What is the net monthly benefit of the preventive programme?

The net monthly benefit is Rs 3,500. Breakdown cost falls from Rs 20,000 to Rs 7,500, a gain of Rs 12,500, but the programme costs Rs 9,000, leaving a net gain of Rs 3,500.

  1. ARs 3,500Correct
  2. BRs 12,500
  3. CRs 9,000
  4. DRs 20,000

Explanation

Breakdown cost now = 4 x 5,000 = Rs 20,000. With preventive: 1.5 x 5,000 = Rs 7,500 plus Rs 9,000 = Rs 16,500. Net benefit = 20,000 - 16,500 = Rs 3,500. Rs 12,500 ignores the programme cost.

Did you get it right without looking?

One question tells you little. A timed set on Economics of Maintenance and Spares Management shows your real accuracy, how long you take and where you lose marks.

More Economics of Maintenance and Spares Management questions