ACCA Applied Knowledge · Management Accounting · Budgetary control and reporting
A manager receives a report showing a large favourable material price variance but an adverse usage variance of similar size. Which interpretation is most appropriate?
The most appropriate interpretation is that cheaper, lower-quality material may have been purchased, leading to more waste and higher usage. Price and usage variances are interdependent, so offsetting amounts should still be investigated rather than ignored.
- ACheaper, lower-quality material may have been bought, causing extra wasteCorrect
- BThe standard price was set too high, so usage must be wrong
- CProduction volume was above budget
- DThe variances cancel out, so no investigation is needed
Explanation
A favourable price with an adverse usage variance often indicates cheaper, poorer-quality materials causing more wastage. Variances are interrelated, so netting them off hides this problem. Volume does not directly cause price or usage variances once flexed.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary control and reporting shows your real accuracy, how long you take and where you lose marks.
More Budgetary control and reporting questions
- Hartley Co has a Production division with a manager who has no authority over insurance policies. Head office charges the division $18,000 f…
- Orla Co's Packing department budgeted controllable costs of $80,000 at 8,000 units. Of this, $24,000 is fixed and the rest is variable. Actu…
- Which of the following is the best description of a controllable cost in the context of responsibility accounting?
- Marlow Co has a semi-variable cost. At 2,000 units the budgeted cost is $14,000 and at 3,500 units it is $19,250. Actual output was 3,000 un…
- A regional manager at Kestrel Ltd is assessed on a departmental budget report. Which of the following costs should be excluded when judging …
- Brandt Ltd's Assembly department budgeted 10,000 units at a variable cost of $12 per unit and fixed costs of $50,000, of which $20,000 is an…