CMA Final · Strategic Cost Management · Network Analysis - PERT, CPM

A PERT network for a warehouse project of Kaveri Constructions has a critical path with an expected duration of 50 days. The variances of the three critical activities are 4, 9 and 3 days squared. Assuming the path duration is normally distributed, what is the approximate probability of completing the project within 54 days? (Area under the normal curve: Z=0.5 gives 0.6915, Z=1 gives 0.8413, Z=2 gives 0.9772.)

The probability is about 84.13%. The critical path variance is 4+9+3 = 16, so the standard deviation is 4 days. Z = (54−50)/4 = 1, and the cumulative normal probability at Z = 1 is 0.8413.

  1. A69.15%
  2. B84.13%Correct
  3. C97.72%
  4. D15.87%

Explanation

Path variance = 4 + 9 + 3 = 16, so the standard deviation is 4 days. Z = (54 − 50)/4 = 1, which gives a probability of 0.8413. The 69.15% option comes from dividing by the variance 16 instead of the standard deviation, and 15.87% is the probability of exceeding 54 days.

Did you get it right without looking?

One question tells you little. A timed set on Network Analysis - PERT, CPM shows your real accuracy, how long you take and where you lose marks.

More Network Analysis - PERT, CPM questions