CMA Final · Strategic Cost Management · Network Analysis - PERT, CPM
A PERT network for a warehouse project of Kaveri Constructions has a critical path with an expected duration of 50 days. The variances of the three critical activities are 4, 9 and 3 days squared. Assuming the path duration is normally distributed, what is the approximate probability of completing the project within 54 days? (Area under the normal curve: Z=0.5 gives 0.6915, Z=1 gives 0.8413, Z=2 gives 0.9772.)
The probability is about 84.13%. The critical path variance is 4+9+3 = 16, so the standard deviation is 4 days. Z = (54−50)/4 = 1, and the cumulative normal probability at Z = 1 is 0.8413.
- A69.15%
- B84.13%Correct
- C97.72%
- D15.87%
Explanation
Path variance = 4 + 9 + 3 = 16, so the standard deviation is 4 days. Z = (54 − 50)/4 = 1, which gives a probability of 0.8413. The 69.15% option comes from dividing by the variance 16 instead of the standard deviation, and 15.87% is the probability of exceeding 54 days.
Did you get it right without looking?
One question tells you little. A timed set on Network Analysis - PERT, CPM shows your real accuracy, how long you take and where you lose marks.
More Network Analysis - PERT, CPM questions
- In a PERT network the critical path has an expected duration of 50 days. The variances of its four activities are 4, 9, 4 and 8 days squared…
- The critical path of a PERT network of Gujarat Pumps Ltd has three activities with these (optimistic, most likely, pessimistic) times in day…
- A critical activity at Sundaram Constructions has a normal duration of 10 days at a cost of ₹50,000 and a crash duration of 7 days at a cost…
- In a project network, activity P has earliest start 6, duration 5, and its successor Q has latest start 14. P has no other successor. What i…
- A PERT network has two paths: A-C and B-D. Three-point estimates (optimistic, most likely, pessimistic, in days) are: A (2, 5, 8), C (4, 7, …
- A network has these activities with durations in days and predecessors: A (3, none), B (4, A), C (6, A), D (5, B), E (2, C), F (3, D and E).…