Which statement about Gantt charts in production control is correct?
Gantt charts are simple to read but show inter-job dependencies poorly. Network techniques like PERT and CPM handle three-time estimates and critical paths. Gantt charts do compare planned and actual progress against a time scale, which is their main strength.
- AThey show the probabilistic time estimates of each activity using three time values
- BThey clearly display the dependency network and critical path of a project
- CThey do not show a link between planned and actual output on a time scale
- DThey are simple to read but show inter-job dependencies poorlyCorrect
Explanation
Gantt charts are easy to prepare and read, but they do not clearly show dependencies between activities; PERT/CPM networks do that. Three-time estimates and critical path belong to PERT/CPM. Option C is wrong since Gantt charts do compare planned and actual progress.
Did you get it right without looking?
One question tells you little. A timed set on Production Planning and Control shows your real accuracy, how long you take and where you lose marks.
More Production Planning and Control questions
- A plant manufactures a wide variety of low-volume, customised products, with each product following a different sequence of operations throu…
- A production manager uses a chart with horizontal bars drawn against a time scale to compare planned and actual progress of jobs on each mac…
- Which statement correctly distinguishes MRP II from basic MRP?
- A plant has 2 shifts of 8 hours each per day and works 25 days a month. It has 10 machines. Effective capacity is 80% of design capacity bec…
- In a master production schedule (MPS), the 'available-to-promise' (ATP) quantity indicates:
- A firm needs an annual output of 24,000 units. Machine A has fixed cost of Rs 3,00,000 per year and variable cost of Rs 20 per unit. Machine…