In a PERT network, an activity has optimistic time 4 days, most likely time 7 days and pessimistic time 16 days. Using the beta-distribution approximation, what is its expected time?
The expected time is 8 days. PERT weights the most likely time four times, so (4 + 4×7 + 16)/6 = 48/6 = 8 days. The simple average of the three estimates would wrongly give 9 days.
- A7 days
- B8 daysCorrect
- C9 days
- D10 days
Explanation
Expected time te = (a + 4m + b)/6 = (4 + 28 + 16)/6 = 48/6 = 8 days. Choosing 9 days would come from the simple average of a, m and b (27/3), which is not the PERT weighting.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- In project crashing under the time-cost trade-off method, which activities should be considered first for shortening the project duration?
- Which of the following best describes resource levelling in project scheduling?
- The critical path of a project at Kaveri Constructions consists of three activities with expected times of 10, 14 and 16 days, and variances…
- In a CPM project network, the critical path is best described as:
- A construction firm in Pune has completed building a warehouse and is now handing it over to the client, obtaining acceptance, releasing sta…
- An activity has optimistic time 6 days, most likely time 9 days and pessimistic time 18 days. What is the variance of its duration under PER…