A project's critical path is 20 days with indirect costs of ₹1,500 per day. Crashing activity X (critical) by 1 day costs ₹1,200 per day, and crashing activity Y (critical) by 1 day costs ₹1,800 per day. Ignoring other paths, which crashing decision lowers total project cost the most?
Crash only activity X. Each day saved cuts ₹1,500 of indirect cost but X costs only ₹1,200 to crash, giving a net saving of ₹300 per day. Y costs ₹1,800 per day, exceeding the saving, so crashing it increases total cost.
- ACrash X only, saving net ₹300 per dayCorrect
- BCrash Y only, saving net ₹300 per day
- CCrash both X and Y, saving net ₹600 per day
- DCrash neither, as crashing always increases total cost
Explanation
Crashing is worthwhile only when the crash cost per day is below the indirect cost saved per day. For X: 1,500 − 1,200 = ₹300 net saving. For Y: 1,500 − 1,800 = −₹300, a net loss. So crash X only; crashing Y would raise total cost. Option claiming crashing never pays ignores X.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- For an activity in a CPM network, the earliest start (ES) is 8 days, duration is 5 days, and the latest finish (LF) is 18 days. What is its …
- Which statement about free float and total float in a CPM network is correct?
- An activity has a normal time of 10 days at a normal cost of ₹40,000 and a crash time of 6 days at a crash cost of ₹52,000. Assuming linear …
- A project has an expected duration of 40 days with a standard deviation of 4 days on its critical path. Given the normal distribution, the a…
- In a project network, a delay in an activity that has a total float of 6 days is 4 days. Assuming no other change, what is the effect on the…
- In PERT analysis, why is the probability of completion by a given date calculated using only the critical path's mean and variance?