A project's critical path is 20 days with indirect costs of ₹1,500 per day. Crashing activity X (critical) by 1 day costs ₹1,200 per day, and crashing activity Y (critical) by 1 day costs ₹1,800 per day. Ignoring other paths, which crashing decision lowers total project cost the most?

Crash only activity X. Each day saved cuts ₹1,500 of indirect cost but X costs only ₹1,200 to crash, giving a net saving of ₹300 per day. Y costs ₹1,800 per day, exceeding the saving, so crashing it increases total cost.

  1. ACrash X only, saving net ₹300 per dayCorrect
  2. BCrash Y only, saving net ₹300 per day
  3. CCrash both X and Y, saving net ₹600 per day
  4. DCrash neither, as crashing always increases total cost

Explanation

Crashing is worthwhile only when the crash cost per day is below the indirect cost saved per day. For X: 1,500 − 1,200 = ₹300 net saving. For Y: 1,500 − 1,800 = −₹300, a net loss. So crash X only; crashing Y would raise total cost. Option claiming crashing never pays ignores X.