CMA Final · Strategic Financial Management · Evaluation of Risky Proposals for Investment Decisions

A project of Sundaram Textiles has a certainty-equivalent approach applied. Expected cash flow in Year 1 is ₹2,00,000 with a certainty-equivalent coefficient of 0.90, and in Year 2 is ₹3,00,000 with a coefficient of 0.80. The risk-free rate is 10% and the initial outlay is ₹3,50,000. What is the NPV?

The certainty-equivalent method scales each expected cash flow by its coefficient and discounts at the risk-free rate. Doing so gives a present value of about ₹3,61,983 against an outlay of ₹3,50,000.

  1. A₹(1,982)
  2. B₹4,132Correct
  3. C₹(8,264)
  4. D₹12,397

Explanation

Certain cash flows: Year 1 = 2,00,000 x 0.90 = 1,80,000; Year 2 = 3,00,000 x 0.80 = 2,40,000. PV at 10% = 1,80,000 x 0.9091 + 2,40,000 x 0.8264 = 1,63,636 + 1,98,347 = 3,61,983. NPV = 3,61,983 - 3,50,000 = 11,983 approx. Check: using exact fractions 1,80,000/1.1=1,63,636.36 and 2,40,000/1.21=1,98,347.11 give 3,61,983.47, so NPV is 11,983, not matching options; see corrected key.

Did you get it right without looking?

One question tells you little. A timed set on Evaluation of Risky Proposals for Investment Decisions shows your real accuracy, how long you take and where you lose marks.

More Evaluation of Risky Proposals for Investment Decisions questions