CMA Intermediate · Operations Management and Strategic Management · Designing of Operational Systems and Control
A plant in Pune uses vibration sensors on its motors and schedules repairs when readings cross a threshold indicating imminent failure. This approach is best described as:
This is predictive maintenance. Repairs are triggered by measured equipment condition, namely vibration readings nearing a failure threshold, rather than by a fixed calendar schedule or by actual breakdown. It aims to service machines just before failure, reducing downtime and avoiding unnecessary servicing.
- ABreakdown maintenance
- BPredictive maintenanceCorrect
- CScheduled overhaul at fixed calendar intervals
- DRoutine lubrication
Explanation
Predictive maintenance uses condition monitoring such as vibration or temperature readings to decide when to service equipment. Fixed calendar overhauls are time-based preventive maintenance, so that option is wrong because the trigger here is the measured condition, not elapsed time.
Did you get it right without looking?
One question tells you little. A timed set on Designing of Operational Systems and Control shows your real accuracy, how long you take and where you lose marks.
More Designing of Operational Systems and Control questions
- A manufacturer in Chennai decides to build extra capacity ahead of expected demand growth, accepting the risk of idle capacity. Which capaci…
- In an assembly line layout, the main purpose of line balancing is to:
- In operations management, the transformation process converts inputs into outputs. Which of the following correctly pairs an input with the …
- Concurrent (simultaneous) engineering in new product development is mainly intended to:
- A plant in Coimbatore has a design capacity of 2,000 units per week and an effective capacity of 1,600 units per week. Its actual output las…
- Sharma Auto Parts has a design capacity of 1,000 units per day. Effective capacity is 800 units per day and actual output is 680 units per d…