CMA Intermediate · Operations Management and Strategic Management · Control Measures - Time and Motion Study, Method Study, Work Study
A time study gives a basic time of 4.00 minutes per piece for a task. The company allows relaxation and other allowances totalling 20% of the standard time (i.e., allowances are expressed as a percentage of the standard time, not of basic time). What is the standard time per piece?
The standard time is 5.00 minutes per piece. Since the allowance is 20% of standard time, basic time forms 80% of it, so 4.00 divided by 0.80 gives 5.00. Adding 20% to basic time would wrongly give 4.80 minutes.
- A4.80 minutes
- B3.20 minutes
- C5.00 minutesCorrect
- D4.20 minutes
Explanation
If allowances are 20% of standard time, basic time is 80% of standard time. Standard time = 4.00 / 0.80 = 5.00 minutes. Check: 20% of 5.00 = 1.00, and 4.00 + 1.00 = 5.00. The option 4.80 wrongly adds 20% on basic time.
Did you get it right without looking?
One question tells you little. A timed set on Control Measures - Time and Motion Study, Method Study, Work Study shows your real accuracy, how long you take and where you lose marks.
More Control Measures - Time and Motion Study, Method Study, Work Study questions
- A flow process chart of a component records: 6 operations, 3 inspections, 4 transports, 2 delays and 1 storage. What is the total number of …
- Which chart is most suitable for recording the movements of the left and right hands of a worker performing a bench assembly task, so that t…
- In a time study at a Pune auto-component unit, the average observed time for an element is 2.00 minutes and the operator's performance ratin…
- A multiple activity chart for a Pune workshop shows that in a 10-minute cycle, the operator works for 6 minutes and is idle for 4 minutes, w…
- Which chart is most suitable for recording the simultaneous activities of a worker and a machine to find idle time of each over a work cycle…
- In a flow process chart, the symbol of a large circle (O) denotes which activity?