A work study engineer at a Hyderabad plant finds standard time of 6 minutes per unit. How many units should a worker produce in an 8-hour shift, if the standard time already includes all allowances?

The worker should produce 80 units. An 8-hour shift has 480 minutes, and with a standard time of 6 minutes per unit that already includes allowances, output is 480 divided by 6, which equals 80 units.

  1. A60 units
  2. B80 unitsCorrect
  3. C48 units
  4. D100 units

Explanation

Shift = 8 × 60 = 480 minutes. Output = 480/6 = 80 units. Since standard time already includes allowances, no further deduction from the shift is needed. 60 would arise by wrongly using 8 minutes per unit.

Did you get it right without looking?

One question tells you little. A timed set on Control Measures - Time and Motion Study, Method Study, Work Study shows your real accuracy, how long you take and where you lose marks.

More Control Measures - Time and Motion Study, Method Study, Work Study questions