CMA Intermediate · Operations Management and Strategic Management · Control Measures - Time and Motion Study, Method Study, Work Study
A time study analyst in a Coimbatore textile mill finds a basic time of 4.50 minutes per piece. Allowances for fatigue, personal needs and delays total 10% of basic time. What is the standard time per piece?
The standard time is 4.95 minutes per piece. Allowances of 10% on a basic time of 4.50 minutes add 0.45 minutes, and standard time is basic time plus allowances, so 4.50 + 0.45 equals 4.95 minutes.
- A4.05 minutes
- B4.95 minutesCorrect
- C5.00 minutes
- D4.55 minutes
Explanation
Standard time = basic time + allowances = 4.50 + 10% of 4.50 = 4.50 + 0.45 = 4.95 minutes. Subtracting the allowance gives 4.05, which is the wrong sign. Dividing by 0.90 gives 5.00, which wrongly treats the allowance as a percentage of standard time.
Did you get it right without looking?
One question tells you little. A timed set on Control Measures - Time and Motion Study, Method Study, Work Study shows your real accuracy, how long you take and where you lose marks.
More Control Measures - Time and Motion Study, Method Study, Work Study questions
- A simo-chart (simultaneous motion cycle chart) is best described as:
- A stopwatch study of a packing task at an Indian FMCG plant records a mean observed time of 1.8 minutes per cycle at a rating of 110. Relaxa…
- In the 'Examine' stage of method study, the questioning technique is applied first to the primary questions. Which set lists the primary que…
- A flow process chart of the existing method at a Pune fabrication shop lists 20 activities: 8 operations, 5 transports, 3 inspections, 2 del…
- A work study engineer at a Hyderabad plant finds standard time of 6 minutes per unit. How many units should a worker produce in an 8-hour sh…
- In a micro-motion study of an assembly task filmed at 1,000 frames per minute, a cycle is recorded as 2,400 frames. A study of the same cycl…