CMA Final · Strategic Cost Management · Network Analysis - PERT, CPM
An activity in a PERT network has optimistic time 10 weeks, most likely time 16 weeks and pessimistic time 28 weeks. What are its expected time and variance respectively?
Expected time is 17 weeks and variance is 9 weeks squared. Expected time is (10 + 4x16 + 28)/6 = 17. The standard deviation is (28 - 10)/6 = 3, and variance is its square, 9. Quoting 3 would confuse standard deviation with variance.
- A17 weeks and 9 weeks squaredCorrect
- B18 weeks and 9 weeks squared
- C17 weeks and 3 weeks squared
- D18 weeks and 3 weeks squared
Explanation
Expected time = (10 + 64 + 28)/6 = 102/6 = 17 weeks. Variance = ((b - a)/6)^2 = (18/6)^2 = 3^2 = 9. Option with 3 weeks squared reports the standard deviation as the variance.
Did you get it right without looking?
One question tells you little. A timed set on Network Analysis - PERT, CPM shows your real accuracy, how long you take and where you lose marks.
More Network Analysis - PERT, CPM questions
- In a PERT network the critical path has an expected duration of 50 days. The variances of its four activities are 4, 9, 4 and 8 days squared…
- The critical path of a PERT network of Gujarat Pumps Ltd has three activities with these (optimistic, most likely, pessimistic) times in day…
- A critical activity at Sundaram Constructions has a normal duration of 10 days at a cost of ₹50,000 and a crash duration of 7 days at a cost…
- A project has a single critical path of three activities, and no other path becomes critical during the crashing considered here. Activity A…
- In a project network, activity P has earliest start 6, duration 5, and its successor Q has latest start 14. P has no other successor. What i…
- A PERT network has two paths: A-C and B-D. Three-point estimates (optimistic, most likely, pessimistic, in days) are: A (2, 5, 8), C (4, 7, …