A project has a single critical path of three activities, and no other path becomes critical during the crashing considered here. Activity A can be crashed by up to 2 days at Rs 4,000 per day; B by up to 3 days at Rs 5,000 per day; C by up to 1 day at Rs 3,000 per day. What is the minimum extra direct cost to shorten the project by 4 days?

The minimum extra cost is Rs 16,000. Crash the cheapest activities first within their limits: C for 1 day costs Rs 3,000, A for 2 days costs Rs 8,000, and B for 1 day costs Rs 5,000. Ignoring the crash limits would understate the cost.

  1. ARs 12,000
  2. BRs 16,000Correct
  3. CRs 18,000
  4. DRs 20,000

Explanation

Crash in order of lowest cost slope: C for 1 day = 3,000; A for 2 days = 8,000; then B for the remaining 1 day = 5,000. Total = 16,000. Rs 12,000 wrongly assumes C can be crashed 4 days, ignoring its 1-day limit.

Did you get it right without looking?

One question tells you little. A timed set on Network Analysis - PERT, CPM shows your real accuracy, how long you take and where you lose marks.

More Network Analysis - PERT, CPM questions