Activity X takes 6 days. The tail event has an earliest time of day 10 and a latest time of day 12. The head event has an earliest time of day 21 and a latest time of day 25. What is the free float of activity X?

Free float is 5 days. It is the earliest time of the head event minus the earliest time of the tail event minus the activity duration, giving 21 − 10 − 6. The 9 days figure is total float, which uses the latest head event time instead.

  1. A9 days
  2. B3 days
  3. C5 daysCorrect
  4. D11 days

Explanation

Free float = earliest time of head event − earliest time of tail event − duration = 21 − 10 − 6 = 5 days. Total float is 25 − 10 − 6 = 9 days, which uses the latest head time. Independent float is 21 − 12 − 6 = 3 days. The 11 days ignores the duration.

Did you get it right without looking?

One question tells you little. A timed set on Network Analysis - PERT, CPM shows your real accuracy, how long you take and where you lose marks.

More Network Analysis - PERT, CPM questions