CA Intermediate · Cost and Management Accounting · Employee Cost and Direct Expenses
Anand Pvt Ltd pays a worker ₹60 per hour for 8 hours daily over 25 working days in a month. Of the 8 hours daily, 1 hour is idle time due to power failure on 10 of those days only, and this is normal idle time. Under proper cost accounting treatment, what is the amount of normal idle time cost and how is it treated?
Normal idle time cost is ₹600, charged to production overheads. Idle hours are 10 days times 1 hour, valued at ₹60 per hour. Because the idle time is normal and unavoidable, its cost is absorbed through overheads rather than written off to the Costing Profit and Loss Account.
- A₹600, charged to production overheadsCorrect
- B₹600, charged to Costing Profit and Loss Account
- C₹1,500, charged to production overheads
- D₹200, charged to direct wages
Explanation
Idle hours = 10 days × 1 hour = 10 hours. Cost = 10 × 60 = ₹600. Normal idle time is an unavoidable part of production and is treated as a production overhead, so it is absorbed by output. Abnormal idle time would go to Costing Profit and Loss Account, which is why the second option is wrong.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- In a factory, the wages paid to workers for the time they were idle because of a power failure that lasted two hours are best treated in cos…
- Under Rowan plan, a worker at Sahyadri Metals has a standard time of 20 hours, a rate of Rs 60 per hour and takes 15 hours for a job. Total …
- In a cost accounting context, which one of the following is classified as 'idle time' of a worker?
- Kaveri Engineering uses the Rowan plan. Standard time for a job is 50 hours, actual time taken is 40 hours, and the rate is Rs 80 per hour. …
- Which of the following is treated as an abnormal idle time cost and is therefore charged to the Costing Profit and Loss Account rather than …
- Under the Halsey premium plan with a 50% share to the worker, a worker is paid Rs 40 per hour. Standard time for a job is 50 hours and he fi…