Dhruv Engineering uses ABC. Its quality inspection pool is Rs 4,80,000, expected to involve 2,400 inspection hours. A customised order needs 150 inspection hours and 500 units. Direct cost of the order is Rs 2,00,000. Using ABC for inspection only, what is the order's total cost including inspection?
The order costs Rs 2,30,000. The inspection rate is Rs 4,80,000 divided by 2,400 hours, which is Rs 200 per hour. The order uses 150 hours, so it absorbs Rs 30,000 of inspection cost, which is added to its direct cost of Rs 2,00,000.
- ARs 2,30,000Correct
- BRs 2,48,000
- CRs 3,00,000
- DRs 2,20,000
Explanation
Rate = 4,80,000/2,400 = Rs 200 per hour. Inspection for order = 150 x 200 = Rs 30,000. Total = 2,00,000 + 30,000 = Rs 2,30,000. Rs 3,00,000 wrongly uses 150 x Rs 200 x 10 style scaling or adds the whole pool; Rs 2,20,000 is another miscalculation.
Did you get it right without looking?
One question tells you little. A timed set on Activity Based Cost Management shows your real accuracy, how long you take and where you lose marks.
More Activity Based Cost Management questions
- Meera Foods Ltd has a distribution activity pool of Rs 9,00,000. The practical capacity is 6,000 deliveries, but only 4,500 deliveries are e…
- Under activity based costing, the cost of 'product design modification', which is incurred for each product line regardless of the number of…
- Under activity based management, a non-value-added activity such as rework of defective output is best handled by:
- Kaveri Textiles has a material-handling pool of Rs 4,80,000 and uses the number of material movements as the driver. Budgeted movements are …
- In an activity based costing system, which of the following is the best example of a batch-level activity?
- In an activity based costing system, which of the following is a unit-level activity whose cost driver is directly proportional to the numbe…