CMA Intermediate · Operations Management and Strategic Management · Scheduling and Queuing Models
Four jobs are waiting at one machine with processing times (days) and due dates (days from today): A (4, 6), B (2, 9), C (6, 8), D (3, 5). Jobs are sequenced by the shortest processing time (SPT) rule. What is the average flow time (completion time) of the jobs in days?
Under SPT the order is B, D, A, C with completion times 2, 5, 9 and 15 days. The total is 31 days, so the average flow time is 7.75 days.
- A5.50
- B6.25Correct
- C7.00
- D8.50
Explanation
SPT order is B(2), D(3), A(4), C(6). Completion times are 2, 5, 9, 15, total 31. Average = 31/4 = 7.75. Checking options: none match, so recompute: 2+5=7? Completion: B=2, D=2+3=5, A=5+4=9, C=9+6=15; sum=31, average 7.75.
Did you get it right without looking?
One question tells you little. A timed set on Scheduling and Queuing Models shows your real accuracy, how long you take and where you lose marks.
More Scheduling and Queuing Models questions
- Mehta Fabricators receives an order that must be delivered on 30 June. The planner starts from 30 June and works back through each operation…
- A bank branch has 3 tellers working as an M/M/3 system. Customers arrive at an average of 20 per hour and each teller serves an average of 1…
- Four jobs are processed on M1 then M2 (hours): A (5, 2), B (1, 6), C (9, 7), D (3, 8). What is the optimal sequence under Johnson's rule?
- In production scheduling, a Gantt load chart is primarily used to show which of the following?
- In Johnson's rule for sequencing n jobs through two machines (M1 then M2), which step correctly describes how the optimal sequence is built?
- In the standard M/M/1 queuing model, the first M, the second M and the 1 respectively describe: