Mehta Engineering absorbs factory overhead on direct labour hours. Budgeted overhead for the year is Rs 6,00,000 and budgeted direct labour hours are 40,000. Actual overhead was Rs 6,30,000 and actual hours were 41,000. What is the overhead under- or over-absorbed?

The predetermined rate is Rs 15 per labour hour. Absorbed overhead for 41,000 hours is Rs 6,15,000 against actual overhead of Rs 6,30,000, so Rs 15,000 is under-absorbed because absorption falls short of actual cost incurred.

  1. ARs 15,000 under-absorbedCorrect
  2. BRs 15,000 over-absorbed
  3. CRs 30,000 under-absorbed
  4. DRs 15,000 over-absorbed with rate Rs 16

Explanation

Rate = 6,00,000 / 40,000 = Rs 15 per hour. Absorbed = 41,000 x 15 = 6,15,000. Actual = 6,30,000. Absorbed is less than actual, so Rs 15,000 is under-absorbed. Rs 30,000 uses budget instead of absorbed overhead for comparison.

Did you get it right without looking?

One question tells you little. A timed set on Job Costing shows your real accuracy, how long you take and where you lose marks.

More Job Costing questions