ACCA Strategic Professional · Strategic Business Leader · Leading and managing projects
Halden Telecom is building a new billing system. The project manager has agreed the scope, but during delivery, sales managers keep requesting extra reports and features, with no formal approval, and the team accepts them to keep the managers happy. The schedule is now slipping and costs are rising. Which project management problem does this best describe, and what is the correct response?
This is scope creep, meaning uncontrolled additions to the agreed project scope. The right response is a formal change control process, so each request is assessed for its impact on time, cost and quality and approved or rejected, rather than quietly absorbed by the team.
- AScope creep; apply a formal change control process to assess and approve each requested changeCorrect
- BPoor resource levelling; hire more staff to speed up delivery
- CRisk transfer failure; pass the extra requests to a supplier by contract
- DBenefits realisation failure; cancel the project and restart with new objectives
Explanation
Uncontrolled additions to agreed scope are scope creep. The remedy is formal change control, where each change is assessed for its effect on time, cost, quality and benefits before approval. Adding staff does not address the cause, and cancelling is disproportionate.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Bramwell Co is planning a product launch project. The activities are: A (3 weeks, no predecessor), B (5 weeks, after A), C (2 weeks, after A…
- Halden Bank's core banking replacement project is reported as 'green' by the project manager each month, based on her own progress reports. …
- Marisol Retail is implementing a new customer data platform. A senior director, Mr Okafor, strongly influences budget decisions but has show…
- Brightwell Renewables is planning a solar farm build. The project manager has divided the project into deliverables (site preparation, panel…
- Marlow Council is planning a new public leisure centre. The sponsor insists on a fixed opening date and a fixed budget, but the stakeholders…
- A project network for Corvane Media's studio refit shows the following activities: A (3 weeks, no predecessor), B (4 weeks, after A), C (6 w…