Halden Ltd is planning a project with a budget at completion of $400,000. After 6 months, the planned value is $200,000, the earned value is $160,000 and the actual cost is $180,000. Assuming current cost performance continues for the rest of the work, which statement is correct?

The project is behind schedule (SPI 0.8) and over budget (CPI 0.889). If current cost efficiency continues, the estimate at completion is the budget divided by CPI, which is $450,000. Adding only the $20,000 variance would wrongly assume the remaining work is on budget.

  1. AThe project is behind schedule and over budget, with a forecast estimate at completion of about $450,000Correct
  2. BThe project is behind schedule and over budget, with a forecast estimate at completion of about $420,000
  3. CThe project is ahead of schedule and under budget, with a forecast of $360,000
  4. DThe project is behind schedule but under budget, with a forecast of $400,000

Explanation

CPI = EV/AC = 160/180 = 0.889, so the project is over budget. SPI = EV/PV = 160/200 = 0.8, so it is behind schedule. EAC = BAC/CPI = 400,000/0.889 = $450,000. The $420,000 figure comes from adding the cost overrun of $20,000 only, which assumes future work goes exactly to budget.