ACCA Strategic Professional · Strategic Business Leader · Leading and managing projects
Halden Ltd is planning a project with a budget at completion of $400,000. After 6 months, the planned value is $200,000, the earned value is $160,000 and the actual cost is $180,000. Assuming current cost performance continues for the rest of the work, which statement is correct?
The project is behind schedule (SPI 0.8) and over budget (CPI 0.889). If current cost efficiency continues, the estimate at completion is the budget divided by CPI, which is $450,000. Adding only the $20,000 variance would wrongly assume the remaining work is on budget.
- AThe project is behind schedule and over budget, with a forecast estimate at completion of about $450,000Correct
- BThe project is behind schedule and over budget, with a forecast estimate at completion of about $420,000
- CThe project is ahead of schedule and under budget, with a forecast of $360,000
- DThe project is behind schedule but under budget, with a forecast of $400,000
Explanation
CPI = EV/AC = 160/180 = 0.889, so the project is over budget. SPI = EV/PV = 160/200 = 0.8, so it is behind schedule. EAC = BAC/CPI = 400,000/0.889 = $450,000. The $420,000 figure comes from adding the cost overrun of $20,000 only, which assumes future work goes exactly to budget.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Brightwell Retail is implementing a new loyalty platform. The project is delivered on time and on budget to specification, but a year later …
- Teskon Energy abandoned a major smart-metering project after the sponsor left, when it emerged that no one had been accountable for the busi…
- Brennick Foods installed a new customer ordering platform. It was delivered on time and on budget, but customers dislike it and sales have f…
- Lumen Foods is launching a new product line. The project risk register shows a risk with a low probability of occurring but a catastrophic i…
- Vantor Pharma is planning a drug-packaging automation project. Its previous three similar projects each overran budget by 25-35%, yet the ne…
- Marlow Pharma has just finished a three-year plant automation project. The board asks for a review to be held after the project's outputs ha…