CMA Intermediate · Operations Management and Strategic Management · Production Planning and Control
In a manufacturing firm, the plan that sets monthly output, workforce and inventory levels for product families over roughly the next 6 to 18 months is called:
It is the aggregate production plan. It determines output rates, workforce size and inventory for product families over a medium-term horizon of about 6 to 18 months, rather than detailing individual items or jobs, which are handled by later short-term schedules.
- AAggregate production planCorrect
- BShop-floor dispatching schedule
- CDetailed operation sheet
- DMaterial requirement purchase order
Explanation
Aggregate planning works at product-family level over a medium-term horizon, deciding output rate, workforce and inventory. Dispatching and operation sheets are short-term, job-level documents, and purchase orders deal with buying, not family-level capacity.
Did you get it right without looking?
One question tells you little. A timed set on Production Planning and Control shows your real accuracy, how long you take and where you lose marks.
More Production Planning and Control questions
- In a Material Requirement Planning (MRP) system, which of the following is the primary input that states the quantity and timing of the fini…
- Product P needs 2 units of sub-assembly S, and each S needs 4 units of part T. For an order of 50 units of P, stock of S on hand is 30 units…
- A plant works one shift of 8 hours per day for 25 days in a month. Each machine is available for 90% of scheduled time, and there are 10 ide…
- In production planning and control, which activity specifically involves fixing the sequence in which jobs will be processed on each machine…
- A production manager uses a chart with horizontal bars drawn against a time scale to compare planned and actual progress of jobs on each mac…
- A plant manufactures a wide variety of low-volume, customised products, with each product following a different sequence of operations throu…