Product P needs 2 units of sub-assembly S, and each S needs 4 units of part T. For an order of 50 units of P, stock of S on hand is 30 units and stock of T on hand is 100 units, with no scheduled receipts. How many units of T must be ordered?

180 units of T must be ordered. Net S is 100 required less 30 in stock, giving 70. Those 70 units need 280 units of T, and after deducting the 100 units of T in stock, the net requirement is 180 units.

  1. A180 unitsCorrect
  2. B300 units
  3. C200 units
  4. D100 units

Explanation

Gross S = 50 x 2 = 100; net S = 100 - 30 = 70. Gross T = 70 x 4 = 280; net T = 280 - 100 = 180 units. Using gross S gives 400 - 100 = 300, which wrongly ignores the S stock netting at the parent level.

Did you get it right without looking?

One question tells you little. A timed set on Production Planning and Control shows your real accuracy, how long you take and where you lose marks.

More Production Planning and Control questions