CMA Intermediate · Operations Management and Strategic Management · Production Planning and Control
Product P needs 2 units of sub-assembly S, and each S needs 4 units of part T. For an order of 50 units of P, stock of S on hand is 30 units and stock of T on hand is 100 units, with no scheduled receipts. How many units of T must be ordered?
180 units of T must be ordered. Net S is 100 required less 30 in stock, giving 70. Those 70 units need 280 units of T, and after deducting the 100 units of T in stock, the net requirement is 180 units.
- A180 unitsCorrect
- B300 units
- C200 units
- D100 units
Explanation
Gross S = 50 x 2 = 100; net S = 100 - 30 = 70. Gross T = 70 x 4 = 280; net T = 280 - 100 = 180 units. Using gross S gives 400 - 100 = 300, which wrongly ignores the S stock netting at the parent level.
Did you get it right without looking?
One question tells you little. A timed set on Production Planning and Control shows your real accuracy, how long you take and where you lose marks.
More Production Planning and Control questions
- A plant manufactures a wide variety of low-volume, customised products, with each product following a different sequence of operations throu…
- In a manufacturing firm, the plan that sets monthly output, workforce and inventory levels for product families over roughly the next 6 to 1…
- In a Material Requirement Planning (MRP) system, which of the following is the primary input that states the quantity and timing of the fini…
- A plant works one shift of 8 hours per day for 25 days in a month. Each machine is available for 90% of scheduled time, and there are 10 ide…
- Which statement about capacity planning is correct?
- Which statement about Gantt charts in production control is correct?