CMA Intermediate · Operations Management and Strategic Management · Production Planning and Control
In a Material Requirement Planning (MRP) system, which of the following is the primary input that states the quantity and timing of the finished products to be produced?
The Master Production Schedule is the primary MRP input that states the quantity and timing of finished products. The bill of materials shows component structure and the inventory file shows stock, but only the MPS drives the gross requirements for end items.
- AMaster Production ScheduleCorrect
- BBill of Materials
- CInventory status file
- DPurchase order register
Explanation
The Master Production Schedule (MPS) specifies how many end items are to be made and when. The Bill of Materials only lists the components needed per unit, and the inventory file records stock on hand and on order. Neither of these states the demand for finished goods over time.
Did you get it right without looking?
One question tells you little. A timed set on Production Planning and Control shows your real accuracy, how long you take and where you lose marks.
More Production Planning and Control questions
- In a manufacturing firm, the plan that sets monthly output, workforce and inventory levels for product families over roughly the next 6 to 1…
- A plant works one shift of 8 hours per day for 25 days in a month. Each machine is available for 90% of scheduled time, and there are 10 ide…
- Which statement about Gantt charts in production control is correct?
- In production planning and control, which activity specifically involves fixing the sequence in which jobs will be processed on each machine…
- A firm needs an annual output of 24,000 units. Machine A has fixed cost of Rs 3,00,000 per year and variable cost of Rs 20 per unit. Machine…
- Which of the following is a pure 'chase' strategy in aggregate planning?