A production manager uses a chart with horizontal bars drawn against a time scale to compare planned and actual progress of jobs on each machine. This tool is best identified as:

The tool is a Gantt chart. It shows jobs or activities as horizontal bars along a time scale, letting managers compare planned schedules with actual progress on each machine. The other charts serve different purposes such as ranking causes, showing break-even, or tracing defect causes.

  1. AGantt chartCorrect
  2. BPareto chart
  3. CBreak-even chart
  4. DIshikawa diagram

Explanation

A Gantt chart plots activities or jobs as horizontal bars against time, so planned and actual progress can be compared. A Pareto chart ranks causes by frequency, a break-even chart relates cost and volume, and an Ishikawa diagram traces causes of a defect.

Did you get it right without looking?

One question tells you little. A timed set on Production Planning and Control shows your real accuracy, how long you take and where you lose marks.

More Production Planning and Control questions