CMA Final · Strategic Cost Management · Activity Based Cost Management
In an activity based costing system, which of the following is the cost driver most appropriately matched to the 'machine set-up' activity in a plant making products in small batches?
The number of set-ups is the right cost driver for machine set-up activity, because set-up costs arise each time a batch changes over and not with units, labour hours or machine hours, which are volume-related measures.
- ANumber of set-ups performedCorrect
- BDirect labour hours
- CUnits produced
- DMachine hours
Explanation
Set-up cost is incurred each time a batch is changed over, so it varies with the number of set-ups rather than with volume. Direct labour hours, units or machine hours are volume-based and would distort product costs for small-batch products.
Did you get it right without looking?
One question tells you little. A timed set on Activity Based Cost Management shows your real accuracy, how long you take and where you lose marks.
More Activity Based Cost Management questions
- In an activity based costing system, which of the following is the best example of a batch-level activity?
- In an activity based costing system, which of the following is a unit-level activity whose cost driver is directly proportional to the numbe…
- Sundaram Auto Components Ltd pools its machine set-up costs of ₹6,00,000 and uses the number of set-ups as the cost driver. Total set-ups in…
- Which one of the following is a unit-level activity under the Activity Based Costing hierarchy?
- A pharma packaging unit in Baddi has a quality-inspection cost pool of Rs 6,00,000 for the year. The cost driver is the number of inspection…
- Narmada Tools Ltd makes two products. Total overhead is Rs 8,00,000, of which Rs 2,00,000 is setup cost driven by number of setups and Rs 6,…