CMA Final · Strategic Cost Management · Activity Based Cost Management
Sundaram Auto Components Ltd pools its machine set-up costs of ₹6,00,000 and uses the number of set-ups as the cost driver. Total set-ups in the year are 400. Product Alpha required 90 set-ups and 30,000 units were produced. What is the set-up cost per unit of Alpha under ABC?
The set-up cost per unit of Alpha is ₹4.50. The cost driver rate is ₹6,00,000 divided by 400 set-ups, which is ₹1,500 per set-up. Alpha used 90 set-ups, so it absorbs ₹1,35,000, which spread over 30,000 units gives ₹4.50.
- A₹1.50
- B₹4.50Correct
- C₹2.00
- D₹6.00
Explanation
Rate per set-up = 6,00,000 / 400 = ₹1,500. Alpha is charged 90 x 1,500 = ₹1,35,000. Per unit = 1,35,000 / 30,000 = ₹4.50. Using 400 set-ups as the base for Alpha's share without applying 90 gives a wrong result.
Did you get it right without looking?
One question tells you little. A timed set on Activity Based Cost Management shows your real accuracy, how long you take and where you lose marks.
More Activity Based Cost Management questions
- Meera Foods Ltd has a distribution activity pool of Rs 9,00,000. The practical capacity is 6,000 deliveries, but only 4,500 deliveries are e…
- Kaveri Components Ltd has a quality inspection cost pool of Rs 3,60,000 with a cost driver of number of inspections, total 1,200 inspections…
- Under activity based costing, the cost of 'product design modification', which is incurred for each product line regardless of the number of…
- Under activity based management, a non-value-added activity such as rework of defective output is best handled by:
- Kaveri Textiles has a material-handling pool of Rs 4,80,000 and uses the number of material movements as the driver. Budgeted movements are …
- In an activity based costing system, which of the following is the best example of a batch-level activity?