CMA Final · Strategic Cost Management · Activity Based Cost Management
Which one of the following is a unit-level activity under the Activity Based Costing hierarchy?
Machine hours used in cutting each unit is a unit-level activity because it is performed for every unit produced and its cost rises in proportion to output. Setups are batch-level, product design is product-sustaining, and building maintenance is facility-sustaining.
- AMachine hours consumed in cutting each unit of productCorrect
- BSetting up a machine for each production batch
- CDesigning a new product variant
- DMaintaining the factory building
Explanation
Unit-level activities are performed every time a unit is produced, so their cost varies with volume, as with machine time per unit. Setup is batch-level, design is product-sustaining, and building maintenance is facility-sustaining.
Did you get it right without looking?
One question tells you little. A timed set on Activity Based Cost Management shows your real accuracy, how long you take and where you lose marks.
More Activity Based Cost Management questions
- Ganga Electronics has two products. Overhead pools: setups Rs 4,00,000 (driver: 100 setups) and packing Rs 2,40,000 (driver: 1,200 packing o…
- Kaveri Components Ltd has a quality inspection cost pool of Rs 3,60,000 with a cost driver of number of inspections, total 1,200 inspections…
- Meera Foods Ltd has a distribution activity pool of Rs 9,00,000. The practical capacity is 6,000 deliveries, but only 4,500 deliveries are e…
- Under activity based costing, the cost of 'product design modification', which is incurred for each product line regardless of the number of…
- Under activity based management, a non-value-added activity such as rework of defective output is best handled by:
- Sundaram Auto Components Ltd pools its machine set-up costs of ₹6,00,000 and uses the number of set-ups as the cost driver. Total set-ups in…