CMA Intermediate · Operations Management and Strategic Management · Production Planning and Control

In line balancing for an assembly line, the sum of all task times is 54 minutes per unit and the required cycle time is 9 minutes. What is the theoretical minimum number of workstations?

The theoretical minimum is 6 workstations, found by dividing total task time of 54 minutes by the required cycle time of 9 minutes. Fewer stations would push the cycle time above 9 minutes, so the target output rate could not be met.

  1. A5
  2. B6Correct
  3. C7
  4. D9

Explanation

Theoretical minimum stations = total task time / cycle time = 54/9 = 6. Five would give a cycle time of 10.8 minutes, exceeding 9. Seven would be possible but not the minimum.