CMA Intermediate · Operations Management and Strategic Management · Economics of Maintenance and Spares Management
In the economics of maintenance, which of the following best describes preventive maintenance?
Preventive maintenance is scheduled servicing done at planned intervals to reduce the likelihood of breakdowns. It differs from breakdown maintenance, which waits for failure, because the aim is to avoid costly stoppages by acting before the equipment fails.
- ARepairing equipment only after it has stopped working
- BScheduled servicing carried out at planned intervals to reduce the chance of breakdownCorrect
- CReplacing all machines every year regardless of condition
- DPostponing all maintenance spending to reduce current costs
Explanation
Preventive maintenance consists of planned inspection, lubrication and servicing at fixed intervals to lower the probability of failure. Option A describes breakdown maintenance. Replacing all machines yearly and postponing spending are not preventive maintenance.
Did you get it right without looking?
One question tells you little. A timed set on Economics of Maintenance and Spares Management shows your real accuracy, how long you take and where you lose marks.
More Economics of Maintenance and Spares Management questions
- A textile mill in Surat replaces the bearings of its looms every 6 months according to a fixed calendar, whether or not the bearings show an…
- In ABC analysis of a spares inventory, which approach is most appropriate for the A-category items?
- A mill at Surat has 50 looms. Past data show the following breakdowns per month under breakdown maintenance: 2 breakdowns with probability 0…
- A machine costs ₹60,000 with zero resale value. Maintenance costs by year are: ₹6,000, ₹9,000, ₹13,000, ₹18,000, ₹24,000 and ₹31,000 for yea…
- Which cost item typically rises as the level of preventive maintenance is increased, while the cost of breakdown losses falls, giving a U-sh…
- A cement plant has a spare part with a daily consumption of 6 units. The lead time is 10 days and a safety stock of 20 units is maintained. …