A cement plant has a spare part with a daily consumption of 6 units. The lead time is 10 days and a safety stock of 20 units is maintained. What is the reorder level?

The reorder level is 80 units. Demand during the 10-day lead time is 6 units a day times 10, which is 60 units, and the safety stock of 20 units is added so production is protected against delays or higher usage.

  1. A80 unitsCorrect
  2. B60 units
  3. C20 units
  4. D86 units

Explanation

Reorder level = consumption during lead time + safety stock = 6 x 10 + 20 = 80 units. Ignoring safety stock gives 60, which is wrong. Adding daily usage again to get 86 is unfounded.