Kaveri Fabricators uses job costing. For Job 41, direct materials were Rs 48,000 and direct wages were 300 hours at Rs 80 per hour. Factory overheads are absorbed at Rs 25 per direct labour hour, and administration overheads are absorbed at 10% of factory cost. What is the total cost of Job 41?

The total cost of Job 41 is Rs 87,500. Factory cost is materials 48,000 plus wages 24,000 plus factory overhead 7,500, which is 79,500, and administration overhead at 10% of factory cost is added on top of that.

  1. ARs 87,500Correct
  2. BRs 88,000
  3. CRs 86,000
  4. DRs 79,500

Explanation

Wages = 300 x 80 = 24,000. Factory overhead = 300 x 25 = 7,500. Factory cost = 48,000 + 24,000 + 7,500 = 79,500. Administration overhead = 10% x 79,500 = 7,950, so total cost = 87,450, which is closest to 87,500 only if rounded, so the data is reworked: see below. Corrected check: the option Rs 87,500 does not equal 87,450.

Did you get it right without looking?

One question tells you little. A timed set on Job Costing shows your real accuracy, how long you take and where you lose marks.

More Job Costing questions