CA Intermediate · Cost and Management Accounting · Overheads - Absorption Costing Method

Kaveri Industries absorbs factory overheads at ₹12 per direct labour hour. Budgeted overheads were ₹6,00,000 and actual overheads incurred were ₹5,70,000. Actual direct labour hours worked were 46,000. What is the amount of overheads under- or over-absorbed?

Overheads are under-absorbed by ₹18,000 (absorbed ₹5,52,000 versus actual ₹5,70,000).

  1. AUnder-absorbed by ₹18,000Correct
  2. BOver-absorbed by ₹18,000
  3. COver-absorbed by ₹30,000
  4. DUnder-absorbed by ₹30,000

Explanation

Overheads absorbed = actual hours × rate = 46,000 × ₹12 = ₹5,52,000. Actual overheads incurred = ₹5,70,000. Since absorbed overheads are lower than actual overheads, there is under-absorption of ₹5,70,000 − ₹5,52,000 = ₹18,000. Budgeted overheads are not used in this calculation.

Did you get it right without looking?

One question tells you little. A timed set on Overheads - Absorption Costing Method shows your real accuracy, how long you take and where you lose marks.

More Overheads - Absorption Costing Method questions