CA Intermediate · Cost and Management Accounting · Overheads - Absorption Costing Method
Gupta Engineering absorbs factory overheads at ₹12 per direct labour hour. Budgeted overheads were ₹6,00,000 for 50,000 direct labour hours. Actual overheads were ₹5,70,000 and actual direct labour hours were 46,000. What is the position of overheads?
Overheads absorbed are 46,000 hours at ₹12, which is ₹5,52,000, against actual overheads of ₹5,70,000. Absorption is lower than actual cost, so overheads are under-absorbed by ₹18,000. Comparing actual with budgeted overheads does not measure absorption.
- AUnder-absorbed by ₹18,000Correct
- BOver-absorbed by ₹18,000
- CUnder-absorbed by ₹30,000
- DOver-absorbed by ₹30,000
Explanation
Absorbed overhead = 46,000 × 12 = ₹5,52,000. Actual overhead = ₹5,70,000. Absorbed is less than actual, so under-absorbed by 5,70,000 − 5,52,000 = ₹18,000. Comparing actual with budget (₹30,000 lower) is the wrong base and gives a false over-absorption.
Did you get it right without looking?
One question tells you little. A timed set on Overheads - Absorption Costing Method shows your real accuracy, how long you take and where you lose marks.
More Overheads - Absorption Costing Method questions
- Vindhya Engineering has two production departments, A and B, and two service departments, X and Y. Primary overheads: A Rs 1,50,000, B Rs 1,…
- Ganga Industries has two production departments, P and Q, and one service department, S. Overheads after primary distribution: P Rs 2,40,000…
- Which statement about the treatment of under-absorbed overheads caused by abnormal factors, such as a prolonged strike, is correct in cost a…
- Sundaram Engineering Ltd. has two production departments, P1 and P2, and two service departments, S1 and S2. After primary distribution the …
- Anand Components Ltd. has production departments X and Y and service departments S and T. Primary overheads: X Rs 50,000; Y Rs 40,000; S Rs …
- Kaveri Textiles has two service departments, S1 and S2, and two production departments, P1 and P2. Overheads before service allocation: S1 ₹…