ACCA Applied Skills · Performance Management · Activity-based costing
Kiln Co makes products P and Q. Overheads are: material handling $92,000 (driver: production batches) and inspection $70,000 (driver: inspections). Batches: P 40, Q 6. Inspections: P 60, Q 40. P: 2,000 units produced, prime cost $39 per unit. What is the total ABC cost per unit of P?
The total ABC cost per unit of P is $100. Batch rate is $2,000 giving $80,000, and inspection rate is $700 giving $42,000 for P. Overhead of $122,000 over 2,000 units is $61 per unit, and adding $39 prime cost gives $100.
- A$100Correct
- B$61
- C$71.40
- D$79
Explanation
Handling rate = $92,000 / 46 batches = $2,000, so P gets $80,000. Inspection rate = $70,000 / 100 = $700, so P gets $42,000. P overhead = $122,000 / 2,000 = $61 per unit; add prime cost $39 = $100. $71.40 results from a single rate per unit ($162,000 / 5,000 = $32.40 plus $39), and $79 ignores inspection cost.
Did you get it right without looking?
One question tells you little. A timed set on Activity-based costing shows your real accuracy, how long you take and where you lose marks.
More Activity-based costing questions
- Which of the following is a typical reason for grouping several activities into a single cost pool in an ABC system?
- Which of the following is a recognised criticism of traditional volume-based absorption costing?
- Rowan Co's order processing cost pool is $48,000 and the cost driver is the number of customer orders, of which there were 1,200 in the peri…
- In an activity-based costing system, which of the following is the most appropriate cost driver for the cost pool 'machine set-up costs'?
- Setup costs at Delta Co total $120,000 for the period, and the cost driver is the number of machine setups. There were 400 setups in total. …
- Which statement about cost drivers in ABC is correct?