In an activity-based costing system, which of the following is the most appropriate cost driver for the cost pool 'machine set-up costs'?
The number of set-ups performed is the best cost driver for set-up costs, because each set-up consumes resources regardless of how many units or machine hours follow. ABC links cost to the activity that causes it, not to production volume.
- ANumber of machine hours worked
- BNumber of set-ups performedCorrect
- CDirect labour hours worked
- DNumber of units produced
Explanation
A cost driver should be the factor that causes the cost of the activity to be incurred. Set-up costs arise each time a machine is set up, so the number of set-ups is the driver. Machine hours and units are volume-based measures and do not reflect what causes set-up cost.
Did you get it right without looking?
One question tells you little. A timed set on Activity-based costing shows your real accuracy, how long you take and where you lose marks.
More Activity-based costing questions
- Setup costs at Delta Co total $120,000 for the period, and the cost driver is the number of machine setups. There were 400 setups in total. …
- Kiln Co makes products P and Q. Overheads are: material handling $92,000 (driver: production batches) and inspection $70,000 (driver: inspec…
- Kora Co absorbs overheads using machine hours. Product X uses 2 machine hours per unit and Product Y uses 1 hour per unit. The overhead rate…
- Compared with a traditional absorption costing system that uses a single direct labour hour rate, what is the usual effect of switching to a…
- Bell Co makes products X and Y. Overheads are: machining $90,000 (driver: machine hours) and setups $60,000 (driver: number of setups). Tota…
- Which of the following is a typical reason for grouping several activities into a single cost pool in an ABC system?