Mehta Constructions has a contract priced at Rs 40,00,000. Cost incurred to date is Rs 30,00,000 and estimated further cost is Rs 20,00,000. Work is 60% complete by cost. Under AS 7, the amount of the expected loss to be recognised as an expense immediately is:
The whole expected loss of Rs 10,00,000 is recognised immediately. Total estimated cost is Rs 50,00,000 against a contract price of Rs 40,00,000, and AS 7 requires the full foreseeable loss to be expensed at once, not spread over the stage of completion.
- ARs 6,00,000
- BRs 4,00,000
- CRs 10,00,000Correct
- DRs 0, since the contract is incomplete
Explanation
Total estimated cost = 30,00,000 + 20,00,000 = 50,00,000, against price 40,00,000, so expected total loss = Rs 10,00,000. AS 7 requires the entire expected loss to be recognised immediately, regardless of stage of completion. Rs 6,00,000 apportions the loss by 60%, which is wrong.
Did you get it right without looking?
One question tells you little. A timed set on Contract Costing shows your real accuracy, how long you take and where you lose marks.
More Contract Costing questions
- Materials sent to a contract site cost ₹6,00,000. At the year end, materials at site are ₹70,000 and materials lost by theft cost ₹20,000. M…
- Under a cost-plus contract, the contractee agrees to pay the contractor:
- Kapoor Builders has a contract priced at Rs 80,00,000. At the year end, cost incurred is Rs 36,00,000 and estimated cost to complete is Rs 4…
- For a contract, costs incurred to date are Rs 40,00,000, work certified is Rs 50,00,000, work uncertified is valued at Rs 4,00,000 at cost, …
- A contract has an escalation clause. The contractor's original estimate used materials Rs 10,00,000 and labour Rs 6,00,000. Actual material …
- Sharma Builders is constructing a bridge. Work certified is ₹40,00,000 and the contractee retains 10% of it as retention money. Cash receive…